Everything set up!

Check-out workplace in Cleanroom A of Yasny AITB

Today the preparations were made in the clean room of the launch base. All the equipment containers have been placed in the clean room and inspected after the shipment. Tomorrow, the first activities will begin on ZACUBE-1 and FUNcube and TRITON-1!

The check-out area for ISL and all of our customers is in the larger of the two clean rooms at the launch base. Luckily, our working area has a nice view on the launchers upper stage “Space Head Module” or SHM, which is also being prepared there.

Tomorrow, the check-out activities begin. For the coming three weeks we will host several teams in half week shifts. The final integration of the ISIPODs on the SHM is planned after the first/second week of November.